Page tree

Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

STP-103 runs from 6 to 13 July 2020 (DOYs 188-195). IORGs from IS instruments are expected + SPICE for CMS and STIX, PHI and EUI for extra flushes of RSCW1 data.

DateEvent or Deadline Comment
9 June 2020Distribution LTP02 output (EFECS, JSON, TMCs) to instrument teamsvia GFTS
17 June 2020Open IOR delivery window for IORsInstrument teams can start delivering IORGs via GFTS - CRRs will be returned automatically (only checking for format issues)
Wed 24 June 202012UTIOR deadlineSOC starts final check and consistency of all IORs, and prepares PORs for MOC
26 June 2020First POR bundle to MOC Early deadline on SOC, to allow iteration on PORs and potentially IORs in case this is needed
Tue 30 June 2020Deadline final version PORs to MOC
6 July 2020Start of STP-103 onboard

...