The existing plan for the Cruise Phase, as built in SOOP Kitchen during SOWG#11 has been revised by SOC and upgraded to
be compatible with the new observation definitions provided by the instrument teams
contain the shift in time for RS checkout window 1, as approved during the mini-SWT (see MLP of Cruise during SOWG#13 (mini-SWT))
optimise the data rates for InSitu payload - see presentation during SWT#24 (see Summary of Plan Optimisation for the In Situ Payload)
contain the updates to the timelines as requested by some RS instrument teams (EUI via email and Metis via UM 9.0)
fix any broken coordinated campaigns between RS instruments: the changes made and remaining questions are documented on Summary of changes made to original Cruise Phase plan for RS payload
- The upgraded plan, in the version prior to SWT#24, is available in SOOP Kitchen: https://solarorbiter.esac.esa.int/soopkitchen/#/planning/plan/MLP%20Feb%202020/941941
Required planning during SWT#24
...