STP-103 runs from 6 to 13 July 2020. Only IORGs from IS instruments are expected.
Date | Event or Deadline | Comment |
---|---|---|
4 June 2020 (TBC) | Distribution LTP02 output to instrument teams | via GFTS |
Open IOR delivery window for IORs | Instrument teams that do not rely on updates can start preparing IORs and delivering IORG via GFTS | |
Deadline final version IORs | SOC starts final check and consistency of all IORs, and prepares PORs for MOC | |
First POR bundle to MOC | Early deadline on SOC, to allow iteration on PORs and potentially IORs in case this is needed | |
Deadline final version PORs to MOC | ||
6 July 2020 | Start of STP-102 onboard |
MIB version to be used: MIB of 15 May (formal name to be added)