Date | Meeting | Preparation for ... | Planning Activity or SGS Test | Output of ... / Feedback on ... |
---|
FEB 2020 LAUNCH |
|
|
|
|
(Mar 2020: Formal FECS delivery for LTP1+2) LTP1 input from MOC only received end April LTP2 input from MOC expected 1 June (moved later in schedule) |
| MOC delivers formal FECS to SOC (delayed due to late delivery input)
SOC prepares formal output LTP 1 and input for LTP 2 confirmation
SOC checks SOOP Kitchen plans for LTP 1+2 against formal FECS, incl. planned disturbancesSOC resolves conflicts with coordinated campaigns in LTP 1, if any. Creation of formal EFECS, TMC, observation timelines for LTP 1Preparation of list of conflicts for LTP 2, if any, as input to SOWG15
|
| Formal Output LTP 1 planning (replaces preliminary output received after SOWG14) (delayed due to late delivery input)
SOC distributes updated, formal products (EFECS, TMC, observations timelines)
and context plan in SOOP Kitchen for LTP-1 = input for IOR writing for STPs in May-June 2020
|
|
| Preparation Cruise Phase MLP(3) - Review PSP coordination (opportunities from Jan 2021 onwards)
- SOC prepares context for Cruise Phase planning (orbit plots, events, ...), using formal orbit
- See MLP of Cruise during SWT#26b (Mar 2020)
|
|
|
30-31 Mar 2020 (ESOC)
3m before Jul-Dec 2020 CANCELLED
| SOWG 15
CANCELLED |
| Cruise Phase LTP02 - Confirmation after FECS delivery (cancelled due to late delivery input)
Observations and SOOP planning for Jul-Dec 2020 (In-Situ only)
Note that LTP2 has been planned already at SOWG14. However, after delivery of the formal FECS by MOC, the plan may need small revisions. |
|
March-April 2020 | SWT 26b (series of PI telecons) |
| Cruise Phase MLP (3): revision of MLP for Cruise & freeze SAP for LTP03 (Jan 2021-June 2021) See MLP of Cruise during SWT#26b (Mar 2020) |
|
end April - start May 2020 |
| MOC delivers formal event skeleton to SOC SOC prepares formal output LTP 1 - SOC checks SOOP Kitchen plans for LTP 1 against formal FECS & PTEL, incl. planned disturbances
- SOC resolves conflicts with coordinated campaigns in LTP 1, if any.
- Creation of formal EFECS, TMC, observation timelines for LTP 1
|
| Formal Output LTP 1 planning (replaces preliminary output received after SOWG14) - SOC distributes updated, formal products (EFECS, TMC, observations timelines)
and context plan in SOOP Kitchen for LTP-1 - = input for IOR writing for STPs 100 & 101 (start 15 June 2020)
- STP schedule: see STP-100 and -101 Schedule
|
May-June 2020: Coordinated NECP campaigns regarding alignment, EMC, IIC (Note: magnetic noise monitored throughout NECP) |
| Based on the outcome of the coordinated NECP campaigns: - Analysis of EMC results, prepare report on potentially EMC noisy activities for discussion during SOWG16
- Analysis of IIC results, prepare report for SOWG16
- Analysis of RS alignment results, prepare report for discussion during SOWG16
|
|
|
Early June 2020 |
| MOC delivers formal event skeleton LTP 2 to SOC SOC prepares formal output LTP 2 - SOC checks SOOP Kitchen plans for LTP 2 against formal FECS & PTEL, incl. planned disturbances
- SOC resolves conflicts with coordinated campaigns in LTP 2, if any.
- Creation of formal EFECS, TMC, observation timelines for LTP 2
|
| Formal Output LTP 2 planning (replaces preliminary output received after SOWG14) - SOC distributes formal products (EFECS, TMC, observations timelines)
and context plan in SOOP Kitchen for LTP-2 - = input for IOR writing for STPs in Jul-Dec 2020
- STP schedule: see STP-102 Schedule and following
|
(Jun 2020: ESTRACK meeting) |
|
|
| Output MLP 3: - SOC prepares pass requests for Jan-Jun 2021 (LTP3) + any roll and offpointing requests for RSCW2 & 3
- MOC formally requests passes from ESTRACK (to be fed into FECS)
|
Jul-Aug 2020 |
| Preparation LTP 3: - Instrument teams review observation definitions for Cruise in SOOP Kitchen
- MOC distributes formal event skeleton for LTP 3
- SOC prepares SOOP Kitchen (obs definitions, (E-)FECS, ...)
- Update context page LTP03 Jan 2021-June 2021
|
|
|
8-10 Sep 2020
3m before Jan-Jun 2021 | SOWG 16 (virtual meeting) |
| - Discussion of NECP results on EMC: Prepare draft list of potentially EMC-noisy activities, for approval by SWT
- Discussion of RS alignment results: Define any actions to be taken before LTP-3 (incl. 2 RS checkout windows)
|
|
Cruise Phase LTP03 : observations and SOOP planning for Jan-Jun 2021, based on FECS & PTEL for LTP03, and results of first RS alignment campaign |
|
| Preparation Cruise Phase MLP(4): - Review PSP coordination (opportunities from Jul 2021 onwards)
- SOC prepares context for Cruise & start NMP planning (orbit plots, events, ...)
|
| Output LTP 3 planning: - SOC distributes formal products (EFECS, TMC, obs timelines)
and context plan in SOOP Kitchen - = input for IOR writing for STPs in Jan-Jun 2021
|
5-9 Oct 2020 9m before Jul-Dec 2021 | SWT 27 (virtual meeting) |
| Cruise Phase MLP (4): revision of MLP for Cruise & freeze SAP for Jul-Dec 2021, incl. start of NMP See: LTP04 July 2021-Sep 2021#Dec2021-MLP:ChangesfromSWT27(Oct2020) Approve list of EMC-noisy campaigns, to be used at start of NMP. |
|
dates & format TBC |
| Preparation of MLP for Nominal Phase - first draft: - needs dedicated meeting with all instrument teams, PSs, SOC
- STILL TO BE SCHEDULED
|
| Output MLP 4: - SOC prepares pass requests for Jul-Dec 2021 + any roll and offpointing requests for RSCW4
- MOC formally requests passes from ESTRACK (to be fed into FECS)
|
(Jan-Feb 2021: ESTRACK meeting) |
| Preparation LTP 4 (+ review downlink situation LTP5): - Instrument teams review observation definitions for Cruise and NMP in SOOP Kitchen
- MOC distributes formal event skeleton for LTP4 & rough pass schedule LTP5
- SOC prepares SOOP Kitchen (obs definitions, (E-)FECS, ...)
- Update context page LTP04 July 2021-Sep 2021 (to be split still over LTP04 July-Sep 2021 and LTP05 Oct-Dec 2021)
|
|
|
24-25 March 2021 | SWT 28 (virtual meeting) | no mission level planning during SWT28 |
|
|
20-21 April 2021 (PM) >2m before Jul-Sep 2021 | SOWG 17 (virtual meeting) |
| Cruise Phase LTP 4: observations and SOOP planning for Jul-Sep 2021 (note change to 3-months-long LTPs) There will be a high-level review of LTP5 (Oct-Dec 2021) as well, based on the preliminary pass schedule received from MOC. |
|
by mid May 2021 (output got distributed on 12 May) |
|
|
| Output LTP 4 planning: - SOC distributes formal products (EFECS, TMC, obs timelines)
and context plan in SOOP Kitchen - = input for IOR writing for STPs included in LTP-4
|
end May 2021 |
|
|
| Pre-LTP TN for LTP5: - SOC requests S/C manoeuvres for LTP5 (Oct-Dec 2021) to Flight Dynamics
|