At SWT#24 (2-4 April 2019), real operations start! Being ~10 months away from launch, the mission level planning of the Cruise Phase with special attention to LTP01 (from end of commissioning until 01 July 2020) should take place.

LTP01 is special because the first 4 months fall within Near Earth Commissioning Phase during which no science operations will be planned. Therefore LTP01 in practice only starts at the start of Cruise Phase and thus covers ~mid May (depending on launch date) to end June 2020.

Preparatory work done by SOC prior to SWT#24

Required planning during SWT#24

Decisions made at meeting


SOOP Kitchen plan - status after SWT#24

https://solarorbiter.esac.esa.int/soopkitchen/#/planning/plan/MLP%20Feb%202020/942